LV Auxiliary Conduits
Method of determination
EstimatedEstimated accuracy
50%string
String Inverter architecture
String Inverter with AC Combiner architecture
string+Central Inverter architecture
centralThis is the number of supply and install conduits for LV auxiliary cables in the site. They are calculated to be twice the amount of PTS/PCU's on site.
✎️️ This quantity is estimated and can be adjusted with no impact on the design outcomes.