LV Auxiliary Conduits

Method of determination
Estimated
Estimated accuracy
50%
string
String Inverter architecture
String Inverter with AC Combiner architecture
string+
Central Inverter architecture
central

This is the number of supply and install conduits for LV auxiliary cables in the site. They are calculated to be twice the amount of PTS/PCU's on site.

✎️️ This quantity is estimated and can be adjusted with no impact on the design outcomes.